You may have heard that every problem report must be closed before approval. That is not what Federal Aviation Administration Advisory Circular 20-189 says—but an open report cannot simply be carried forward without a disciplined assessment and an understandable record.
Short answer: Some problem reports may remain open at approval when they are classified, assessed, documented, and justified through an established process. A significant open problem without sufficient mitigation or justification for its safety effect should be resolved before approval. The certification authority may be involved in the disposition.
Open does not mean unmanaged
A problem report is the record used to identify and track anomalous behavior, a failure to follow an approved development process, or a deficiency in life-cycle data. An open problem report, usually shortened to OPR, is a problem report that has not reached the closed state when the product is approved or a Technical Standard Order article is authorized. A Technical Standard Order, or TSO, establishes minimum performance standards for specified materials, parts, processes, or appliances used on civil aircraft.
The distinction between open and closed matters. AC 20-189 describes four states: recorded, classified, resolved, and closed. A recorded problem has entered the reporting process. A classified problem has been assigned a category under the applicant’s classification scheme.
A resolved problem has been corrected or fully mitigated, and the resolution has been verified. It is not yet closed until a formal review confirms that the resolution is effective. That means “resolved” and “closed” are not interchangeable labels, and a team should not change a report’s state merely to improve the appearance of a milestone summary. These states are defined in AC 20-189 paragraph 4.2.
The advisory circular is built around the fact that a problem may still be open at approval. It does not say that the existence of an OPR is automatically unacceptable. Instead, it provides a common process for managing OPRs across the system, software, and airborne electronic hardware domains so that important issues do not lose visibility as information moves among stakeholders.
That process should exist during initial certification and later product changes. Problems discovered after approval should also enter the problem-reporting process, and any related systemic process issue should be identified and corrected. If one stakeholder cannot resolve a problem, the information should be communicated in terms the affected stakeholder can understand. These expectations appear in AC 20-189 paragraph 5.
For a small team, the practical starting point is therefore not “How do we make the open count zero?” It is “Can we show what each report means, who is affected, what controls it, and why its current disposition is acceptable?”
Classification starts with effect
AC 20-189 calls for an OPR classification scheme that includes at least four categories: Significant, Functional, Process, and Life Cycle Data. The scheme belongs in the appropriate planning documents, and each OPR should receive one classification. If more than one category appears applicable, the report receives the highest-priority applicable classification: Significant first, followed by Functional, Process, and Life Cycle Data. See AC 20-189 paragraphs 4.3 and 6.1.
A Significant OPR has an actual or potential effect that may lead to a Catastrophic, Hazardous, or Major failure condition, or may affect compliance with operating rules. A Functional OPR has an actual or potential effect on a function at the product, system, or equipment level. A Process OPR records a process noncompliance or deficiency that cannot produce a potential safety or functional effect. A Life Cycle Data OPR concerns a deficiency in a life-cycle data item that is not tied to a process noncompliance or process deficiency.
These are not labels chosen from the wording of the report title. Classification depends on the effect at the relevant equipment, system, or product level and on the mitigations that can legitimately be credited.
The person classifying the OPR should document mitigations that are known and under that stakeholder’s control. A mitigation controlled by someone else may be considered only when it has been validated with that stakeholder and remains acceptable within the applicable approval. If installation details could move the classification between Functional and Significant, a stakeholder other than the aircraft type-certificate or supplemental type-certificate applicant should classify it as Significant.
A documented formatting deficiency in life-cycle data that has no process, safety, or functional effect is not assessed the same way as anomalous behavior that can affect an aircraft function. The first still needs a justified classification and record; the second requires assessment of its functional and safety consequences, any restrictions, its technical cause, and any mitigation being credited.
The lesson is not that one category is harmless. It is that the classification tells reviewers which questions must be answered and prevents a low-priority label from concealing a higher-priority effect.
Assessment turns a report into a decision
Classification is only the beginning. AC 20-189 paragraph 6.2 says each OPR should be assessed for resulting functional limitations or operational restrictions, relationships with other OPRs, and—for Significant or Functional reports—the underlying technical cause.
Those three parts address different risks. Limitations and restrictions identify what the equipment or product cannot safely or reliably do while the problem remains. Relationships among reports help reveal whether several apparently separate symptoms share a cause or combine into a larger effect. Cause analysis provides the technical basis for understanding and controlling Significant and Functional problems.
The assessment must also match the level at which the decision is being made. AC 20-189 recognizes stakeholders at the item, equipment or TSO-article, system, and product levels. A mitigation visible to a component developer may not be the same mitigation credited by the system or aircraft applicant. Likewise, an installation assumption may not be under the component developer’s control.
This is why an OPR may be classified differently by different stakeholders. The difference is not automatically an inconsistency. It may reflect different validated mitigations and different knowledge of the installation. What matters is that the classification at each level is supportable and that information reaches the stakeholders responsible for the next decision.
The applicant remains responsible for the overall problem-reporting process across the participating stakeholders. OPR management should occur, at a minimum, at the TSO-article level, at each individual system level within a product, and at the product level. AC 20-189 paragraph 7 assigns those responsibilities so that an issue does not disappear at an organizational boundary.
Before a certification milestone, review each open report with questions such as:
- Is the affected configuration identified precisely?
- Does the classification reflect the highest-priority applicable effect?
- Are credited mitigations controlled by this stakeholder or validated with the stakeholder who controls them?
- Are functional limitations and operational restrictions identified?
- Are relationships with other OPRs recorded?
- Is the underlying technical cause understood for every Significant or Functional OPR?
- Can the receiving system or product stakeholder understand the report without reconstructing the developer’s internal context?
This work should be complete before the final certification review becomes the first time the whole story is assembled. AeroCert’s explainer on what the FAA examines during Stage of Involvement reviews provides additional context for how evidence matures across a software program.
The summary must be understandable across stakeholders
AC 20-189 paragraph 6.4 calls for an OPR summary report that is provided to affected stakeholders and made available to the certification authority upon request. The report may aggregate information from software and hardware accomplishment summaries and system-level reports. Aggregation does not remove the need to provide access to the supporting information for each OPR.
For every report, the summary should make the following clear:
- the OPR’s identifier;
- the affected configuration items or processes;
- a title or concise summary understandable to affected stakeholders;
- a description of the problem in equally understandable terms;
- the conditions under which the problem occurs;
- the classification and assessment results; and
- known relationships with other OPRs.
Additional content depends on classification. For a Significant OPR, the record should describe the mitigation or justification used to establish the acceptability of the safety effect, along with any functional limitations or operational restrictions. For a Functional OPR, it should describe how mitigation or justification reduces the safety effect to Minor or No Safety Effect and identify any limitations or restrictions.
For a Process OPR, the record should describe the extent or nature of the process noncompliance or deficiency that may affect satisfaction of the applicable development-assurance objectives. For an OPR that is neither Significant nor Functional, the record should justify why the error cannot produce a safety or functional effect.
The phrase “understandable to the affected stakeholders” is especially important for a small company working with suppliers, integrators, and an aircraft applicant. An internal shorthand understood by the software team is not enough if the system safety team cannot identify the affected behavior, operating conditions, or credited mitigation. The summary should support a decision at the next level, not merely prove that a tracking record exists.
A TSO authorization holder has a limited reporting provision in AC 20-189 paragraph 6.5. Process and Life Cycle Data OPRs that are unnecessary for installation approval may be excluded from the paragraph 6.4 reporting process. All OPRs should nevertheless remain available to the certification authority upon request for assessment within the TSO approval.
Disciplined reporting is easier when it develops with the product rather than being reconstructed at the end. The related AeroCert article about the airborne software-development-assurance standard, Why DO-178C costs more when compliance starts late, explains why contemporaneous records, controlled baselines, and traceability reduce avoidable rework.
What must be resolved before approval
The clearest disposition rule appears in AC 20-189 paragraph 6.3. A Significant OPR that lacks sufficient mitigation or justification to establish the acceptability of its safety effect should be resolved before approval. Disposition may require coordination with the certification authority.
That statement has two practical consequences. First, calling a problem “known” does not make it acceptable. Second, a mitigation is useful only when it is sufficiently substantiated, appropriately controlled or validated, and acceptable within the applicable product or TSO-article approval.
Other classifications still require complete, credible records. A Functional OPR needs support for reducing its safety effect to Minor or No Safety Effect. A Process OPR needs an assessment of the process deficiency and its possible effect on applicable development-assurance objectives. A Life Cycle Data OPR needs justification that the error cannot have a safety or functional effect.
AC 20-189 describes an acceptable means of compliance and states that its guidance is not legally binding on its own. Conformity is voluntary. If an applicant chooses this means, however, the AC says it should be followed in all applicable respects unless an alternate means is proposed and accepted by the FAA. The project-specific certification basis and coordination with the responsible authority still control the final compliance finding.
Before presenting the OPR set for approval, make sure the team can distinguish three outcomes without ambiguity:
- reports that have been corrected or fully mitigated and are moving through formal closure;
- reports that may remain open because their classification, assessment, mitigation, limitations, and justification support acceptability; and
- Significant reports that must be resolved because the safety effect is not acceptably mitigated or justified.
An open problem report is not acceptable because it is documented; it is acceptable only when its effect, classification, assessment, mitigation, and disposition support the approval decision.
As a next step, use AeroCert’s free public-tier checklist library to review the broader planning, requirements, development, verification, configuration-management, tool-qualification, and certification evidence surrounding your OPR process. It provides seven plain-language DO-178B/C checklists (88 checkpoints), free to use and share, covering the DO-178B and DO-178C airborne software-assurance standards. It is not an OPR-specific checklist.
Primary source:
- FAA Advisory Circular 20-189, Management of Open Problem Reports, issued September 16, 2022. Paragraphs 4 through 7 provide the definitions, classification, assessment, disposition, reporting, and stakeholder-responsibility guidance discussed here.
This article is educational guidance. It does not replace the applicable certification basis, project-specific FAA coordination, a qualified authorized representative, or an FAA finding of compliance.
Leave a Reply